Project Name

NW 20th Avenue Lid - NW Raleigh St. to NW Upshur St.



Bid/Contract #

Bid Number 00000894



Awarding Agency

City of Portland



Project Location

Portland, Multnomah County, OR



Bid Date

06/05/2018 at 02:00



Project Details

The NW 20th Avenue LID project involves the construction of street improvements along the
following streets.

- NW 20th Avenue from NW Raleigh Street to NW Upshur Street
- NW Thurman Street from NW 19th Avenue to NW 21st Avenue.
- Intersection of NW 23rd Avenue/NW Vaughn Street/U.S. 30 on and off-ramps.
- NW Savier St between NW 21st and NW 19th Avenues

Improvements shall consist of those items of work listed in the Proposal and as shown on the accompanying Plans. The Contractor shall perform all labor, and furnish all materials, equipment and incidentals required to make each item complete. Work shall include, but not be limited to:

1. Construct, maintain, and remove temporary work zone traffic control measures.
2. Construct, maintain, and remove erosion control measures.
3. Perform all removal of structures and obstruction, clearing and grubbing, and earthwork operations.
4. Construct drainage system including water quality facilities, sewer pipes, manholes, laterals, and inlets.
5. Diversion of flow of existing sewers under construction.
6. Construct roadway improvements including aggregate base, MWMAC wearing
surfaces, concrete curb and sidewalks.
7. Place pavement markings and striping
8. Install signing
9. Install illumination
10. Install traffic signals
11. Roadside development including fencing

D/M/W/ESB Aspirational Goal: 20% (up to 5% for suppliers)

D/M/WBE Utilization Goal: 14%

Subcontracting and material/supply opportunities include (but are not limited to):
- Aggregate supply
- Asphalt Grinding
- Asphalt Paving
- Concrete Flatwork
- Concrete Supply
- Contaminated Soil Remediation
- Erosion Control
- Flagging
- Landscape
- Signs - Electrical
- Signs - Traffic
- Striping
- Survey
- Traffic Control
- Trucking

James W. Fowler Co. is an equal opportunity employer and we are requesting qualified subcontractor and supplier bids from all interested firms, including disadvantaged, minority, women, and other business enterprises. Where economically feasible, we are willing to divide total contract requirements into smaller portions or quantities to permit maximum participation by M/W/DBE firms. Please contact us to discuss opportunities available.

James W. Fowler Co. will assist M/W/DBE subcontractors in obtaining necessary equipment, supplies, or materials. We are also available to provide assistance in obtaining bonding, lines of credit and/or insurance to M/W/DBE subcontractors. Please complete all negotiations 24-hours prior to bid opening. We also encourage the utilization of apprentices for this project.



Please follow the link below for Specifications, Plans and Addenda:

http://www.jwfowler.com/subcontractors/




Copyright © 2024, DBE GoodFaith, Inc. All rights reserved.