FLINT Design Build
is seeking qualified DVBEss


Project Name

LPC New STEAM Building- Inc 1 Site Demolition and Utilities



Bid/Contract #

2411



Awarding Agency

FLINT Design Build



Project Location

Livermore, Alameda County, CA



Bid Date

11/19/2024 at 02:00



Project Details

NOTICE IS HEREBY GIVEN that FLINT, the selected Lease-Leaseback Entity, will receive bids for the Site Demolition and Utility Package, located at 3000 Campus Hill Drive, Livermore, CA 94551. All bids shall be submitted via Building Connected. A link to Building Connected can be found at https://flintbuilders.com/bidding/.

BP#1- Field Engineering
BP#2- Site Safety and Protection (For Reference Only)
BP#3- Demolition and Abatement
BP#4- Earthwork
BP#5- Site Utilities
BP#6- Site Mechanical Piping
BP#7- Site Electrical
BP#8- Site Carpentry
BP#9- Fencing
BP#10- Early Procurement (For Reference Only)

Sam Cannon
FLINT
Sr. Estimator



Plans & Specifications:
DSA Submittal Plans, INC 01_DWG_V1
DSA Submittal Specifications, INC 01_SPC_V1

Bonding: Not required for subcontractors who are prequalified with FLINT.

The subcontractor shall include in his/her bid all labor, materials, equipment, taxes, and insurance, as required for a complete scope of work and in conformance with the contract documents. The project requires prevailing wages be paid to all on site workers and adherence to the Project
Labor Agreement. Refer to Exhibit 1.6. for a copy of the PLA.

Bid Documents available for download: 10/25/24
Pre-Bid Meeting (non-mandatory) date: 10/31/2024 @ 10:00 AM
Cut-off for RFI’s: 11/08/2024 @ 2:00 PM
Final addendum issued: 11/14/2024 @ 2:00 PM
Subcontractor Bid Date: 11/19/2024 @ 2:00 PM
Anticipated start of construction: February, 2025
Anticipated project completion: August, 2025