Sewer Collection System Pipeline Rehabilitation and Replacement Project Phase 8
45-146.08
Oro Loma Sanitary District
San Lorenzo , Alameda County, CA
02/27/2025 at 14:00
Cratus, Inc. is requesting quotes from certified Disadvantaged Business Enterprises, including SBE, MBE, WBE, Subcontractors, Suppliers & Haulers for the construction of the Oro Loma Sanitary Districts Sewer Collection System Pipeline Rehabilitation and Replacement Project Phase 8. The project has not established specific goals, but participation is highly encouraged.
Then project includes the replacement of 12,749 linear feet of 6 and 8-inch vitrified clay pipe (VCP) with 8-inch high density polyethylene pipe (HDPE); 3,327 linear feet of 8-inch VCP with 10-inch HDPE pipe; 1,399 linear feet of 10-inch VCP with 12-inch HDPE pipe; and the reconnection of all laterals and re-channelization of all manholes, as shown on the plans and specifications.
The engineers Estimate is $6,500,000.00
Quotes are requested from qualified Subcontractors, Suppliers, & Haulers for all scopes of work, including but not limited to; SWPPP, BMP & Exclusion Fence Installation, Traffic Control, Saw-Cutting, Demolition, Excavation & Backfill, Trenchless Casing installation/ Boring, Instrumentation & Monitoring, Groundwater well destruction, Asphalt Paving, & Striping, Trucking, and all Other Required Work.
Suppliers are required for materials including Piping & Aggregates.
The plans and specs are available for your review at our office or can be viewed on the Oro Loma Sanitary Districts website.
http://engr.oroloma.org/projects/validate.asp
You will need to register with the district to view the plans.
Please contact our office with any questions or for help with bidding, bonding, or insurance. We are an equal opportunity employer. Bonds will not be required from qualified subcontractors.